BREEAM Assessments
Stroma Design undertakes BREEAM assessments for all schemes:
- Education
- Office
- Retail
- Industrial
- Health Care
|
- Multi-Residential
- Courts
- Prisons
- Bespoke
- In-Use
|
Stroma Design can assess the energy efficiency and sustainability of a commercial or public building using BREEAM. There are three stages to the BREEAM assessment procedure:
- Pre-assessment
The first stage in the BREEAM assessment provides advice that allows for an early informal view of the sustainability of a development and provides advice on the elements that need to be incorporated into the detailed design and cost plan. For more on this stage click here.
- Interim Assessment
The interim BREEAM assessment is usually carried out at RIBA stages C to D once the detailed drawings, calculations and specifications are available. For more on this stage click here.
- Final Certified Assessment
The final certified BREEAM assessment is carried out just prior to hand over and is based on the as built drawings, calculations and a site inspection.
For more on this stage click here.

Pre Assessment Advice
- Provision of a facilitation meeting, during which base design parameters will be explored against the relevant BREEAM criteria
- Review of current scheme information with regards to the BREEAM criteria.
- Provision of pre-assessment document indicating the baseline rating and suggesting what uplift in specifications would be required to reach the desired rating.
- Provision of a Target/Planning document indicating the target credit rating
- Provide advice on BREEAM issues as required.
Certified Interim Assessment
- Issue of an Information Required Schedule to design team
- Review information submitted for formal assessment.
- Provision of interim reports indicating what has been achieved and listing further information required.
(3 interim reports assumed)
- Formal Initial Assessment.
- Attend meeting to go through any outstanding information or issues raised during the formal assessment.
- Provision of Final Design report.
- Issue to BRE for Interim Certification.
Certified Final Assessment
- Issue of Information Required Schedule to the design team
- Review as built drawings and specification against Interim information
- Onsite inspection to verify construction.
- Provision of interim reports indicating what has been achieved and listing further information required.
(2 interim reports assumed)
- Formal PCR assessment.
- Provision of Final Report